Congleton Link Road
The Congleton Link Road will join the A534 Sandbach Road (to the west of Congleton) with the A536 Macclesfield Road (to the north of the town), reducing town centre traffic congestion, cutting pollution, and improving air quality in the surrounding areas.
The scheme will bring economic and social regeneration to Congleton by supporting new development sites and improving access to jobs at Radnor Park Industrial Estate and Congleton Business Park. Graham Construction have been appointed by the Council to deliver the Link Road.
Outline project timeline:
● Ground Investigation works - commenced October 2018
● Detailed Design - commenced October 2018
● Utility Diversions - commence - January 2019
● Ecological Management works - commence January 2019
● Site Compounds established - March 2019
● Main Earthworks works commence - March 2019
● Back Lane East, Somerford, complete - June 2019
● Full Scheme complete - late 2020